Projects
A selection of completed projects in energy plant engineering and industrial construction. The projects include process units for waste-to-energy, boiler pressure parts, steel structures, facade systems and turnkey industrial buildings. For each project we state the scope of supply and the key technical parameters.
Energy



Manufacture and installation of a boiler economiser, Ostrava Hazardous Waste Incineration Plant
Our role
Manufacturing, supply, dismantling, installation
Scope
Manufacture of pressure equipment to the client's drawings. Manufacture of the economiser tube coils including the flue gas duct, 3 separate blocks joined only during installation, fitted with a hopper at the bottom. Dismantling of the existing economiser and installation of the new one, including insulation and cladding.
Key figures
3 separate economiser blocks joined during installation, flue gas duct with hopper, handed over within the outage period



Manufacture of a complete boiler assembly for Kovosta-fluid
Our role
Manufacture of pressure equipment, supply
Scope
Manufacture of pressure equipment to the client's drawings. Manufacture and supply of a complete boiler assembly to the customer's requirements, ready for installation.
Key figures
26.2 t boiler assembly weight, complete assembly ready for installation


Only provider in the Czech Republic
Repair of Kaplan turbine stay vanes, Štěchovice Power Station
Our role
Design of the repair procedure, execution of the repair
Scope
Design of a special repair procedure for the cavitation-damaged parts of the vanes, meeting the requirements on shape and surface roughness after the final repair. Repair of all stay vanes, including replacement of 1 vane. Weld build-up of cavitation damage, peening of welds, grinding and polishing to templates. The work was carried out using a special procedure under strict conditions and in confined spaces.
Key figures
All stay vanes repaired, 1 vane replaced, shape and surface roughness ground and polished to templates



Supply and installation of stainless steel bearing cooling piping, Dlouhé Stráně Power Station
Our role
Pipe sizing, manufacturing, installation
Scope
Pipe sizing to maintain the required cooling water flow. Replacement of end-of-life steel piping with stainless steel. Manufacture and installation from semi-finished elbows, fittings and pipes. Increased requirements on weld quality.
Key figures
2 turbine-generator sets TG1 and TG2, stainless steel piping, cooling water flow verified by measurement



Installation and start-up of the boiler K12 technology, Komterm Kopřivnice
Our role
Design review and modifications, design, manufacturing, installation, complete delivery
Scope
Review of the design and partial modifications to it, optimisation of the connection to the existing plant. Installation of the wood chip boiler and its connections, that is, economiser, valves, pumps, connection to the hot water system and integration into the plant. An additional part was our own design and calculation of the economiser, the design documentation, its manufacture, installation and connection to the hot water system.
Key figures
1 wood chip boiler K12, 1 economiser of our own design, calculation and manufacture, complete delivery from design to start-up

Manufacture and installation of the pressure assembly of boilers K5 and K6, Trmice Heating Plant
Our role
Consultation on the repair solution, manufacturing, supply, dismantling, installation
Scope
Consultation with the customer on the repair solution for boilers K5 and K6. The repair was carried out with our own resources, including in-house manufacture of the steam superheaters, that is, the tube coils. Supply, dismantling of the existing superheaters and installation of the new ones, including insulation, cladding and temporary works.
Key figures
approximately 73 t of tube coils (steam superheaters), 2 boilers K5 and K6


Replacement of superheaters II and IV including headers on boilers K1 to K6, Mělník Power Station
Our role
Manufacture of pressure equipment, dismantling, installation
Scope
Manufacture of pressure equipment to the client's drawings. Tube coils of steam superheaters II and IV including headers. Dismantling of the existing superheaters and installation of new ones on six boilers K1 to K6 in accordance with the client's documentation and requirements.
Key figures
63 t of pressure parts, 6 boilers K1 to K6, 2 steam superheaters per boiler



Conversion of the start-up boiler house to gas firing, Chvaletice Power Station
Our role
Manufacturing, dismantling, installation, start-up
Scope
Manufacture of a new OKP 25 boiler as a designated pressure assembly. Dismantling of the old boiler and installation of the new one, including installation of an economiser and a new gas burner. Supply of pressure and non-pressure parts, including refractory linings, insulation and cladding. Start-up of the equipment.
Key figures
22 t of pressure and non-pressure parts, 1 new OKP 25 boiler, 1 new gas burner

Modernisation of boiler passes I and II, Ostrava Hazardous Waste Incineration Plant
Our role
Repair design, manufacturing, supply, dismantling, installation
Scope
Replacement of approximately one third of the boiler, from the flue gas inlet to the hopper. The brief required a feasible dividing plane for the replacement and completion of all operations within a short time. Manufacture of membrane wall panels, tube bending around wall openings, assembly into walls and installation. The supply included pressure and non-pressure parts, including refractory linings, insulation and cladding.
Key figures
30 t of pressure and non-pressure parts, approximately one third of the boiler replaced, handed over within the outage period
Construction



Architectural facade of the Victoria Palace residential building, Prague
Our role
Supply of facade fins and glass balustrades
Project type
Architectural facade
Scope
Supply of facade fins and glass balustrades, section 04 GLASS. The facade combines glass, aluminium and steel. The critical point is where the materials meet, that is, anchoring, expansion and joint tightness, because each material expands differently with heat and transfers loads differently. Manufacturing tolerances had to remain identical across the entire surface, otherwise any deviation would have been visible on the building.
Building and location
Residential building on Vítězné náměstí, Prague 6



Hyundai car showroom, Uherský Brod
Our role
General contractor
Project type
General contracting
Scope
General contracting of the building. The investor dealt with a single partner for the entire building, and RUBING was responsible for coordinating the trades. The building combines a sales area and a service area with different requirements. The showroom is a visible space where glazed surfaces and precise detailing are decisive. The service area is an operational space where durability and maintenance are decisive. Both were built in one building to one schedule.
Building and location
Sales and service building for a car brand, Uherský Brod



PTÁČEK office and retail centre, Žilina
Our role
General contractor
Project type
General contracting
Scope
General contracting of a building combining a retail hall and a two-storey office section. RUBING led the construction as the single contractor, and the investor dealt with one partner. The hall and office sections have different spans, floor build-ups and indoor environment requirements, so combining them in one building determines the layout, expansion joints and routing of services. The building is in Slovakia, so the design documentation and final building approval follow Slovak regulations.
Building and location
Building combining a retail hall and a two-storey office section, Žilina, Slovakia



P.V.N. shopping centre, Tábor
Our role
Supplier of steel structures and cladding
Project type
Cladding
Scope
Supply of steel structures and cladding for a shopping centre combining several separate tenant units. The building has one envelope and several clients inside, each tenant with its own requirements for layout, utility connections and building services. The deadline is set by the lease agreements, because each tenant opens on an agreed day.
Building and location
Shopping centre with several tenant units, Tábor



Refurbishment of the cladding and lighting of operational buildings, Dětmarovice Power Station
Our role
General contractor in a consortium of STAMONT, RUBING and EDĚ
Project type
Cladding
Scope
Refurbishment of the cladding and lighting of operational and production buildings. RUBING was a member of a consortium of contractors and was responsible for its part of the supply. The other parts were supplied by other consortium members, so this reference does not cover the refurbishment of the entire site. Production at the site continued, and the schedule followed outages and operational constraints.
Building and location
Operational and production buildings of Dětmarovice Power Station



Building envelope, plumbing and drainage and the boiler house HVAC process unit, Ledvice Power Station
Our role
Supplier of the building envelope, plumbing and drainage, the boiler house HVAC process unit and other packages, including construction documentation
Project type
Cladding and process units
Scope
Three separate contracts over the five years of the unit's construction. Lightweight building envelope based on built-up cladding with an exposed face of trapezoidal sheeting. Plumbing and drainage installations. The boiler house HVAC process unit, that is, heating, ventilation and air conditioning. RUBING produced the construction documentation for its own supplies, so design and execution remained with one supplier. The reference does not cover the construction of the unit as a whole.
Building and location
Supercritical unit of Ledvice Power Station, the tallest industrial structure in the Czech Republic



Extension to the DEKTRADE office building, Olomouc
Our role
General contractor
Project type
Turnkey extension
Scope
General contracting of the office building extension. RUBING led the construction as the single contractor, so the investor did not have to coordinate the trades. With an extension, the critical points are the connection of the load-bearing structure to the existing building, the expansion joint between the old and new parts and the continuity of the envelope with the existing facade. The original building remained in use, and construction could not interrupt access or utilities.
Building and location
Office building at the DEKTRADE building materials site, Olomouc


Warehouse 1, ROCKWOOL Bohumín
Our role
General contractor, manufacture and installation of the steel structure and cladding
Project type
Turnkey industrial building
Scope
General contracting of the warehouse. In-house manufacture and installation of the load-bearing steel structure. Supply and installation of the cladding. The building adjoins the existing production site, so installation took place next to running operations, with restricted transport routes and divided work areas.
Building and location
Warehouse at the ROCKWOOL Bohumín site, a centre for industrial and technical insulation

Roofing and cladding of the Škoda Auto automated high-bay warehouse, Mladá Boleslav
Our role
Supply and installation of the roofing, cladding, drainage system and central heating
Project type
Cladding and roofing
Scope
Supply and installation of the roofing, including panels. Supply of the cladding, drainage system and central heating. On a warehouse roof of this size, tightness and drainage capacity are decisive, the falls and outlets are designed for torrential rain and the envelope must carry the snow load. A leak above an automated operation affects the technology, not just the building. The supply did not include the load-bearing structure of the warehouse or the storage technology.
Building and location
Automated high-bay warehouse, Mladá Boleslav


Cladding of the main production block, Tušimice II Power Station
Our role
Supplier of the cladding, including the supporting steel structure and associated trades
Project type
Cladding
Scope
Replacement of the cladding of the main production block in two stages. Dismantling of the original envelope including the supporting steel structure. Supply and installation of a new supporting steel structure and new cladding. Supply of central heating, ventilation and electrical installations with measurement and control. The schedule was set by the comprehensive renewal project, and the deadlines of both stages were fixed. The power station technology was supplied by other companies, and the reference does not cover it.
Building and location
Main production block of Tušimice II Power Station as part of the comprehensive renewal of the power station